Daily Care
Daily:
Strap Seal・・・・・・・・・・・・ Check the seal for good bond & overlap.
Abnormal Noise ・・・・・・・・・・ Check for any abnormal noise during machine operation
Vibration ・・・・・・・・・・・・・・・・ Check for any abnormal vibration during machine operation.
Power ・・・・・・・・・・・・・・・・・・・Check for splits / breakage in power cord. Replace if damaged.
Weekly:
Clean the inside of the machine ・・Remove strap dust, paper dust, foreign matters with compressed air.
Clean the heater blade (top & bottom) with wire brush, steel wool or emory cloth (only after heater cools)
Blow out debris from the internal fan.
Monthly:
*Lube center press bar & slide table with oil (Part #4NA76)
To prevent injury please be sure the tabletops are replaced prior to
operation.
CHAPTER 6 ADJUSTMENT
Adjustment of
VR3
at insufficient tension
VR 3 is a volume that adjusts the completion of band reversal before tightening. VR3 is on the
control board.
If tightening begins before the reverse rotation is completed, adjust VR3 by turning it clockwise.
If reverse rotation is not completed even though the band is wrapped around the packing item,
turn VR3 counterclockwise to make adjustment.