INSTALLATION, START-UP & MAINTENANCE MANUAL
MODEL NO.: SD-820 / SD-1710
REV 1 – AUGUST 03,.2001
Page 50
SECTION 7
7.5 SHUT-DOWN IN CASE OF A FAULT OR FOR MAINTENANCE
Danger!
Before any kind of maintenance or repair work is
done, the adsorption dryer must be depressurized
and disconnected from the power source.
Apply the general safety regulations!
* Advices
The following sequence is to be heeded when switching off the adsorption dryer:
Switch off the dryer when the dryer transfers into the repressurization step,
or at any time when both chambers are at full pressure.
Close all the shut off valves up- and downstream of the adsorption dryer,
Depressurize the dryer by using the hand valve mounted at the bottom of the
after-filter.
7.6 RE-STARTING
Close the hand valve mounted at the bottom of the after-filter.
Slowly open the inlet isolation valve and pressurize the adsorption dryer up
to the regular operating pressure by keeping the shut off valve mounted
behind the after-filter closed
Switch on the unit once again.
If the adsorption dryer is re-started after a long standstill, proceed as in 3.1.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sullair SD Series and is the answer not in the manual?