Commissioning
30 NT 10000...NT 12000
NOTE
For a better understanding of keyboard operation, please also see the chapter
Operation.
The procedure for commissioning the Solar Inverter as a
single unit
and as a main unit and secondary units with several networked units
is described in detail below.
Please note:
Once the system has been commissioned, the country can no longer be changed
via the menu. To change the country retrospectively, please contact the Techni-
cal Hotline on
Tel +49 (0)7531 996 77-577.
Commissioning single unit
System with one Solar Inverter
1. The commissioning process starts with setting of the display language. Se-
lect the language in selection menu with / .
Confirm the selected language with .
2. Select the country in the selection menu with / .
3. Confirm the country of installation with .
NOTE
The Solar Inverter only starts feeding current into the grid once the country has
been selected.