Explains the double case rotary meter construction and operating principle.
Provides general guidance and safety for disassembly procedures.
Lists essential tools and equipment required for meter disassembly.
Details the process for removing the outer cover and packing gland.
Covers the maintenance schedule and procedure for the packing gland.
Outlines the steps for servicing and disassembling the packing gland.
Describes the removal of the gear train components from the meter cover.
Explains the procedure for checking and adjusting rotor end clearance.
Details the specific rotor adjustment procedure for C2 through G6 models.
Outlines the rotor adjustment procedure for H8 and JA10 models.
Provides instructions for removing the inner mechanism from the meter housing.
Details the steps to remove rotor cover rollers and associated components.
Highlights specific differences for the C2 series meter during disassembly.
Lists recommended minimum and maximum fitting clearances for repaired meters.
Explains how to measure blade slot clearance using feeler gauges.
Details the method for checking blade top end clearance with a micrometer.
Describes how to measure blade tip to housing clearance using a spider and feeler gauge.
Outlines the procedure for measuring rotor to block clearance.
Explains how to check blade roller to cam radius clearance.
Presents an alternative method for measuring blade roller to cam radius difference.
Details the procedure for adjusting total end clearance of the rotor.
Provides a template for recording meter clearance measurements.