CG-SVX039C-GB
9
Pre-Installation
Installation requirements and contractor responsibilities
A list of the contractor responsibilities typically associated with the unit installation process is provided.
Type of requirement
Trane-supplied
Trane-installed
Trane-supplied
Field-installed
Field-supplied
Field-installed
Foundation • Meet foundation requirements
Rigging
• Safety chains
• Clevis connectors
• Lifting beams
Isolation
• Neoprene Pads
• Isolators
(Optional)
• Neoprene Pads
• Isolators (Customer Supplied)
Electrical
• Disconnect
Switch
• Unit mounted
starter
• Wiring sizes per submittals and local codes and
regulations
• Terminal lugs
• Ground connection(s)
• BAS Wiring (optional)
• Control voltage wiring
• Chilled water pump contactor and wiring
including interlock
• Option relays and wiring
Water piping
• Flow Switch
• Water Strainer
(Optional)
• Taps for thermometers and gauges
• Thermometers
• Water ow pressure gauges
• Isolation and balancing valves in water piping
• Vents and drains
• Pressure relief valves
• Pressure switch device to detect lack of water
Insulation • Insulation • Insulation (Piping)
Water piping connection elements • Grooved pipe
• Grooved pipe
couplings (or)
Flanged Adapters