4 UNT-PRC002-GB
Technical Data
FWD 08 12 20 30 45
Power supply (V/Ph/Hz) 230/1/50
Capacities
Cooling capacity on water (1) (kW) 5,2 8,3 15 18,8 30,1
Heating capacity on water (2) (kW) 6,3 11,9 18,9 20,9 38,2
Fan motor (type) 2 x direct drive centrifugal
Fan power input (3) (kW) 0,23 0,46 0,65 1,04 1,51
Current amps (3) (A) 1,1 2,2 3,1 4,7 5,5
Start-up amps (A) 3,2 5,5 9,3 14,1 16,5
Air flow
minimum (m
3
/h) 490 980 1400 1800 2700
nominal (m
3
/h) 820 1650 2300 3000 4500
maximum (m
3
/h) 980 1970 2600 3600 5400
Main coil
Water entering/leaving connections (type) ISO R7 rotating female
(Dia) 3/4" 3/4" 1 1/2" 1 1/2" 1 1/2"
Electric heater (accessory for blower only)
Electric power supply (V/Ph/Hz) 230/1/50 230/1/50 or 400/3/50 400/3/50 400/3/50 400/3/50
Heating capacity (kW) 2/4 8 10 12 12
Hot water coil (accessory for blower only)
Heating capacity (4) (kW) 6,3 12 17,4 22,4 34,5
G2 filter (filter box accessory)
Quantity 2 2 2 2 2
Dimensions ( LxWxth) (mm) 386x221x8 486x271x8 586x321x8 586*421*8 586*621*8
G4 filter (filter box accessory)
Quantity - 2 2 2 2
Dimensions ( LxWxth) (mm) - 486x264x48 586x314x48 586*414*48 586*614*48
Condensate pump (accessory) (type) Centrifugal
Water flow - lift height (l/h - mm) 24 - 500
Not available for FWD30 and FWD45
Sound level (L/M/H speed)
Sound pressure level (5) (dB(A)) 36/40/43 38/41/44 46/50/53 47/52/57 47/52/58
Sound power level (5) (dB(A)) 46/50/53 48/51/54 56/60/63 57/62/67 57/62/68
Unit dimensions
Width x Depth (mm) 890 x 600 1090 x 710 1290 x 820 1290 x 970 1290 x 1090
Height (mm) 250 300 350 450 650
Shipped unit dimensions
Width x Depth (mm) 933 x 644 1133 x 754 1333 x 864 1333 x 1008 1333*1133
Height (mm) 260 310 360 460 660
Weight (kg) 32 46 61 76 118
Colour galvanised steel
Recommended fuse size
Unit alone (aM/gI) (A) 8/16 8/16 8/16 8/25 8/25
Unit with electric heater (gI) (A) 16 (2kW),25 (4kW) 40 (230V),3*16 (400V) 3*20 3*25 3*25
(1) Conditions: Water entering/leaving temperature: 7/12 °C, Air inlet temperature 27/19°C DB/WB - Nominal air flow
(2) Conditions: Water entering/leaving temperature: 50/45 °C, Air inlet temperature 20°C DB - Nominal air flow
(3) At high speed with nominal air flow.
(4) Water entering/leaving temperature 90/70 °C, air inlet temperature 20 °C DB, Nominal air flow.
(5) A rectangular glass wool duct 1m50 long is placed on the blower.The measurement is taken in the room containing the blower unit.
Heat exchanger operating limits:
FWD:
*water temperature: max 100° C
*absolute service pressure: min 1 bar/max 11 bars
Accessories - Hot water coil:
*water temperature: min. +2° C/max. 100° C
*absolute service pressure: min 1 bar/max 11 bars
CG-SVX051A-GB
62
Compressor Service Information
Mechanical Compressor Failure
Replace the failed compressor(s) and change the oil in
the remaining compressor(s) along with the refrigerant
system liquid line filter drier.
Electrical Compressor Failure
Replace the failed compressor and change the oil in
the other compressor(s). Also add a suction filter with
cleanup cores and change the liquid line filter drier.
Change filters and oil until the oil no longer test acidic.
See “Oil Testing.”
Compressor Motor Megging
Motor megging determines the electrical integrity of the
compressor motor winding insulation. Use a 500 volt
megger. A less than 1 meg-ohm reading is acceptable
and 1000 ohms per nameplate volts is required to safely
start the compressor.
Compressor Current Imbalance
Normal current imbalance could be 4 to 15 percent
with balanced voltage due to motor design. Each phase
should register 0.3 to 1.0 ohms and each phase should
be within 7 percent of the other two phases. Phase to
ground resistance must be infinity.
NOTICE: Maximum allowable voltage imbalance is 2
percent.
Compressor Electrical Terminal Box
Be sure to protect the terminal box when unbrazing or
brazing compressor refrigerant piping connections.
Compressor Crankcase Heaters
Compressor crankcase heaters must be energized at
least eight hours before starting the unit. This is required
to boil refrigerant out of the oil before startup. ambient
temperature is not a factor and the crankcase heaters
must always be energized prior to startup.
Refrigerant Piping
The compressor suction and discharge connections
and piping are copper clad steel for easy brazing. In
most instances, piping may be reused. If piping is not
reusable, order the correct service parts. Cut all tubing
with a tubing cutter to prevent copper filings from
entering the system. Cut the tubing in a straight length
of pipe after the compressor connection has been
unsweated. The line can then be reinstalled using a slip
coupling and brazing.
NOTICE: The compressor suction line configuration
must not be changed in any way. Changing compressor
suction line configuration will compromise proper oil
return to the compressor(s).