STEP 4 - Install a clean-out tee in the primary
drain line for future maintenance. It is recom-
mended that you install a cap on the top of the
tee.
STEP 5 - Insulate the primary drain line to
prevent sweating where dew point temperatures
may be met. (Optional depending on climate
and application needs.)
Provide a means of drainage to prevent winter
freeze-up of condensate line. (Optional depend-
ing on climate and application needs.)
STEP 6 - Support the condensate piping outside
the unit per local codes for proper drainage and
to prevent sagging.
Allow 1/4” of downward slope for each foot of
pipe.
Insulation
Condensate
Piping
Supports
Cap
Tee
3” minimum
clearance is
recommended
from cabinet to
inside edge of
tubing
3” min.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane TAM4A0C48S41SB and is the answer not in the manual?

Trane TAM4A0C48S41SB Specifications

General IconGeneral
BrandTrane
ModelTAM4A0C48S41SB
CategoryAir Handlers
LanguageEnglish

Related product manuals