3578 • CB500 VENDOR | 3
UNPACKING
This vending machine was thoroughly inspected before leaving the factory and the
delivering carrier has accepted this
vendor as their responsibility. Note any
damage or irregularities at the time of
delivery and report them to the carrier.
Request a written inspection report
from the claims inspector to file any
claim for damage. File the claim with
the carrier (not the manufacturer)
within 15 days after receipt of the
vending machine.
Carefully remove the outside packing
material so as not to damage the finish
or exterior of the vending machine.
Inspect the vending machine for
concealed shipping damage.
Report any damage hidden by the
shipping material directly to the delivering carrier on a Hidden Damage Report.
Record the model number and serial number of the vendor for your records. These
numbers can be found on the Serial Plate on the rear of the cabinet and/or inside
the vendor. Refer to these numbers on all correspondence and inquiries pertaining
to this vendor.
Remove the “Knock-A-Way” support by sliding a pallet jack under the vendor,
inserting a screwdriver or prying tool into the groove of the “Knock-A-Way” and
splitting it in two as shown in Figure 1. Turn the leveling screws in as far as
possible.
INSTALLATION
INSTALLATION CHECKLIST
□
All shipping brackets, packing material and tape are removed.
□
Vendor is properly leveled from left to right and front to back.
□
*Vendor is positioned no more than six feet from the power outlet.
□
There is a space of at least four inches between the back of the vendor and
any wall or obstruction, to allow proper air circulation.
□
*Vendor is plugged directly into a properly polarized and grounded (earthed)
dedicated circuit.
□
Bottom kick panel is installed on the bottom of the door.
□
Vendor has been properly loaded and all items in each selection corresponds
to the display product and vend price. Refer to Live Display selection below.