Initial Start-up and Service
20
Steps (continued)
17. Check and adjust ignition and ionization electrode
Service
1. Remove burner cover panel (if still
installed) as per the removal and
reinstallation instructions on page 7
in this manual, and reinstall panel
upon completion of service work.
2. Check electrodes for wear and
contamination.
3. Clean electrodes with small brush or
emery paper.
4. Check clearances. If clearances are
not satisfactory or the electrodes are
damaged, replace electrodes and
gasket A and align.
Tighten fastening screws for the
electrodes to a torque of 1.5 lb.ft. /
2Nm.
18. Check condensate drain
Service
Ensure condensate drains freely (e.g. at
siphon trap
).
If necessary, clean siphon trap.
Discharge tubing
Flexible discharge tubing
Siphon trap
If the condensate does not drain freely,
condensate will accumulate in bottom
part of boiler resulting in a burner
shut-down (fault message).
Installation Instructions
Neutralization Unit
(if applicable)
5285 961 v1.3
Do not damage wire mesh when
cleaning.
CAUTION
8
+4
5
+3
3
+0.5
+0
7
-1
-0
-0
-0
IMPORTANT