Commissioning
Tests before commissioning 7.2
Ground conditions
The maximum dumping height depends on several factors of the ground
conditions. An exact specification of this value is not possible.
Determine the maximum fill height by compaction tests or soil sam-
ples.
Shaking in cobblestones
To avoid damage to the machine or compaction material, use a slid-
ing device, see Accessories on page 46.
Compaction of asphalt
To avoid cracking and sticking to the asphalt, use water tank with
sprinkler system, see Accessories on page 46.
7.2 Tests before commissioning
Information
Further information and detailed descriptions, see Mainte-
nance on page 37.
Perform the following checks:
Check machine and components for damage.
Do not put the damaged machine into operation. Damages and
defects must be repaired immediately.
Check the fuel level.
Check fuel lines for leaks.
Check air filter.
Check engine oil fill level.
Check to ensure the screw connections are firmly seated.
Check control elements for functionality.
7.3 Putting into operation with Briggs & Stratton engine
WARNING
Danger of burns due to starting aid sprays!
Starting aid sprays can ignite and cause severe burns.
Do not use any starting aid sprays.
[en-US] | Version: 5 | 04/2023 | 5100066824 | BPS1030B, BPS1135B, BPS1340B, BPS1550B, BPS2050B | BPS |
Operator’s Manual 33
7

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson BPS Series and is the answer not in the manual?