Maintenance
Maintenance work 9.3
35
[en] | 07/2022 | 5100056271 | BS-2 | Operator’s Manual
Activity Daily
Weekly
25 h
Once a
month
100 h
2 Monthly
200 h
3 Monthly
300 h
Once a
year
Check fuel lines and connections for
cracks and leaks, replace if necessary.
Check screw connections of rammer foot
plate, retighten if necessary.
Clean engine cooling fins.
Clean spark plug and check gap.
Oil change:
Ramming system
1
Relubrication interval:
Ramming system
Check central suspension for wear, dam-
age or misuse.
Replace spark plug.
Clean fuel filter, have it changed if neces-
sary.*
1
Change oil after first 50 hrs.
* Have this work carried out by a service partner.
9.3 Maintenance work
9.3.1 Carrying out preparations
1. Place the machine on a level surface.
2. Decommissioning the machine.
3. Let the machine cool down.
9.3.2 Cleaning the machine
1. Clean machine and components after each use.
2. The manufacturer recommends cleaning with compressed air.
3. Wipe the housing with a damp and clean cloth.
4. After cleaning, check cables and wires for damage.
5. Check screws and bolts to see if they are loose.
6. Remedy any deficiencies noted immediately.
9

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson BS-2 and is the answer not in the manual?