17 Maintenance
The panels of the smoke and heat exhaust ventilation system have to be checked, serviced and, if necessary, repaired at least
once per year by the manufacturer or an authorized partner
Remove all soiling from the units of the smoke and heat exhaust system. Check fastening and clamping screws for firm seating.
Carry out a test run of the entire system (see chapter 15 ‘Commissioning and test run).
Only have defective units repaired in our factory. Only install original spare parts.
Check the operational condition at regular intervals. We recommend a WindowMaster service contract is taken out to ensure the
right function of the smoke and heat exhaust system.
All back up batteries coming with the smoke control panel as standard; have to be subjected to regular checks.
The smoke ventilation panel will signal fault on the batteries if the battery voltage is below 17V.
Within the framework of the service, they have to be replaced after the specified maximum 4 year operating period.
Dispose of used batteries according to the National regulation.
CAUTION: RISK OF EXPLOSION IF BATTERIES ARE REPLACED BY AN INCORRECT TYPE.
We recommend that the software of the panel is updated during the annual maintenance check!
The expected minimum lifetime for the CompactSmoke™ is 10 years excluding the batteries.
17.1 Maintenance agreements
Be aware that regular inspection of smoke ventilation systems is a legal requirement. The legislation requires that the smoke
ventilation system's owner inspects and tests the system once every year.
WindowMaster offer maintenance agreements for the smoke ventilation system and every year we inspect the complete system
to ensure it complies with the applicable legislation. Maintenance of the smoke ventilation system includes checking windows,
window actuators and emergency power and checking that triggering and control functions are fully functional.
Contact our service department for further information: telephone +44 1536 510990 or info@windowmaster.co.uk
17.2 Replacement 3SS card
1. Disconnect the 230 V and the batteries.
2. Insert the 3SS replacement card.
3. Turn on the 230 V and connect the batteries.
4. The system will be ready again after approx. 2 seconds.
18 Declaration of Conformity and Declaration of Perfomance
The smoke ventilation panels are manufactured and tested accordingly to the European requirements.
The total system is not to be put into service until a declaration of conformity for the total system has been made.
The “Declaration of Conformity” and the EN certificate are supplied with panel as separate documents.