NSFD minimum run timer - 5 minutes
NFSD test PR timer - 20 seconds
4. Adjust any other settings in order to meet the needs of your system.
5.2.9 Test the package
1. Exit the setup menu.
2. Stop the package.
3. Press the Auto key and then Start.
4. Observe the pressures and temperatures for normal operation.
5. Press the Alternation key and observe the operation of each pump.
6. Close the running water faucet.
It is assumed that no demand for water is required. For example, no flow.
7. Observe the No Flow Shutdown sequence. All minimum run timers must elapse for this
sequence to occur.
8. Demand water from the system and observe the restart of the package.
If you encountered no problems, then you are done.
5 Commissioning, Startup, Operation, and Shutdown