Introduction to the manual 13
2
Introduction to the manual
Contents of this chapter
The purpose of the manual is to assist in commissioning the ACS580MV frequency
converter. It includes necessary instructions, practical hints and references to related
documentation to successfully commission the converter and the related equipment as
needed for the application.
Scope of commissioning
Normally, the commissioning engineer is only responsible for the converter. If agreed by
contract, the commissioning engineer who have gained the related certification can take
on the commissioning of:
Motor
MCB / protection relays
Manual / Sync Bypass unit, (MSS, MB)
Requirement for reports
During the commissioning the Field Service Report and Commissioning Report should be
prepared, which are generated by the DriveStartup tool.
Service engineer shall upload the commissioning report within one month after
commissioning, or upload the service report within one week after the service.
NOTICE Commissioning of the converter may only be carried out by personnel who
have been certified with “Basic” or above training level.