EasyManua.ls Logo

ABB ACS580MV - Inspection of Installation

ABB ACS580MV
150 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
22 Standard Commissioning Process
Motor
Motor is installed, aligned and alignment protocol is available.
Motor is not coupled to the driven load.
Grounding is completed in compliance with local regulation.
Motor auxiliaries (bearing lubrication, heater cooling etc.) are ready.
Control and monitoring signals are connected. If this option is available.
Customer side motor protection set and ready. (e.g. winding temperature, vibration)
The user manual and technical specification is available.
Insulation of the motor has been tested according to manufacturing specifications. The
official test report must be available.
Power
Medium voltage is available for start-up of the converter.
Low voltage auxiliary power is available for start-up of the converter.
Low voltage space heater power is available. If this option is available.
Miscellaneous
Sufficient number and correct type of spare parts are available.
Desk and chair used for commissioning is available. Office power terminal is available.
The infrastructure of the electric room is finished and the installation site is sufficiently
ventilated or cooled and dehumidification to ensure the converter can running at the
appropriate temperature and humidity.
If operation with open doors filter of the room is available.
It is not allowed to operate with open door or windows of the electrical room if air is not
filtered.
Air conditioning or ventilating duct of the drive room is ready for load run of the
converter. Regarding last two options, window of electrical room should be with filter.
Air condition
Nature air cooling
Ventilating duct
Inspection of installation
In order to achieve a trouble-free commissioning, it is mandatory that the installation,
including third-party equipment, is inspected upon arrival.
The status of the installation is checked and it is verified that converter and related
equipment meet the applications specification. It should be verified that the installation is
done according to the installation instructions and the applicable safety regulations have
been met.
Check the installation with the guidance of the DriveStartup tool and the above Pre-
Commissioning Check Lists in Checking the pre-conditions for commissioning. Information
about installed equipment which is required by the report must be obtained and noted in
the corresponding sections of the report.

Table of Contents

Other manuals for ABB ACS580MV

Related product manuals