68 Standard Commissioning Process
Cold commissioning
All necessary inspection
Inspection of converter installation.
Check if the power cable connection on the secondar side of the integrated
transformer is correct.
NOTICE The connection of power cable must be solid. It is not allowed to have any
washer between two cable lugs. The tightening torque should follow ACS580MV
Hardware Manual (2UBB004520).
passed case
failed case