34 Standard Commissioning Process
3. Inform customer send remote MCB close/open CMD, and measure voltage as below
table. The values should not be higher than 5V.
Remote MB CMD drawing
Other checking items
Before energizing the Auxiliary supply for the first time, proceed as follows:
1. Make sure that all auxiliary switches, optional circuit breakers and protection switches
inside the drive have been switched off.
2. Before turning on the fuses and breakers, measure the incoming auxiliary voltage and
control voltage, verifying that it is within +/- 10% of the rated value.
Probe+ Probe- AC DC
X1:42 PE < 5V < 5V
X1:44 PE < 5V < 5V
X1:46 PE < 5V < 5V
X1:48 PE < 5V < 5V
X1:50 PE < 5V < 5V
X1:52 PE < 5V < 5V