Standard Commissioning Process 35
3. Confirm that the installation and wiring of the cooling fan is correct if the fan has been
removed by customer. When the cooling fan needs removing for some reason, just
pull off the left side plug.
Cooling Fan wiring
4. If XDI interface on BCON is used, please disconnect XDI terminals and inform
customer send instruction accordingly to confirm there is no input voltage, otherwise
X10, X90 can be damaged.
5. If XAI, XAO interfaces on BCON are used, please confirm input of XAI should be 0(2)-
10V or 0(4)-20mA, higher input can damage BCON.
BCON customer interface