Standard Commissioning Process 21
Converter integrated transformer
Transformer is in good condition after transportation.
The primary tap is at the same level (-5% / 0% / +5%) if this option is available. If the
network voltage is at the correct level of converter requires, just 0% tap of 3 phase
need to be shorted. The tap level should be shorted based on the actual network
voltage to match the converter requires.
The PT100 inside the transformer is in good condition.
Power modules
The DC link capacitors need to be reformed (re-aged) if the converter power module has
been nonoperational for more than one year. Without reforming, capacitors may get
damaged when the power module starts to operate.
Check the power module age.
Serial number of power module defines the week when it was manufactured. For
example, 2UBA916040009:
16: denotes manufacturing year (2016).
04: manufacturing week.
0009: running manufacturing number.
Regarding the instruction of reforming, refer to the documentation: ACS580MV PM
Capacitor Reforming Instructions (2UBB017371).
BCON board
Provide below information, ask for the license from MV Drives Supportline:
Series number of the drive
Series number of the BCON board, including the board as spare parts.
Note: The position of BCON series number is shown hereunders.