46 Standard Commissioning Process
In this step, only select Install Cable Drivers. Till to finish successfully.
Switch off the control power.
Remove the daughter boards DB2 and DB3 to get access the X5 connector on control
hub.
Connect XILINX platform cable USB II to X5 connector on control hub.
Switch on the control power.