Standard Commissioning Process 93
Complete the site condition report ‘2UBB021641_ACS580MV Drive and Site
Condition Check List’, together with the commissioning report (service report) and field
service report, add to the attachment.
Update all the drive data and reports to MoR by pressing ’Upload ALL to Installed
base (MoR)’ button.