Introduction to this manual 19
Installation, commissioning and operating flowchart
Task See
Identify the frame size of your drive, R7 or R8.
Technical data
(page 99)
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection,
compatibility of the motor, motor connection,
and other technical data.
Select the cables.
Technical data
(page 99)
Planning the electrical installation
(page 37)
Option manual (if optional equipment is included)
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Unpacking the unit
(page 33)
If the converter has been non-operational for more
than one year, the converter DC link capacitors
need to be reformed.
Capacitors
(page 95)
Check the installation site.
Before installation
(page 34)
Technical data
(page 99)
If the drive is about to be connected to an IT
(ungrounded) system, check that the drive is not
equipped with EMC filter +E202.
Note: You cannot disconnect the EMC filter.
Type code
(page 27)
Route the cables.
Routing the cables
(page 62)
For compliance with the European Union EMC
Directive, see
CE marking
(page 125)
Check the insulation of the motor and the motor
cable.
Checking the insulation of the assembly
(page 63)
Install the drive. Connect the power cables.
Connect the control and the auxiliary control
cables.
Electrical installation
(page 63),
Resistor braking
(page 131) (optional)
Commission the drive. Appropriate firmware manual