Operation Manual / 4 Product description / A130-H.. - A140-H
3 Commissioning / 3.3 Commissioning after taking out of operation
© Copyright 2020 ABB. All rights reserved. HZTL4030_EN Rev.F February 2020
3.3 Commissioning after taking out of operation
If present
u Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
gas outlet.
u Remove the screw plugs on the water connections and fit the water pipe.
Version with compressor wheel cooling:
u Remove the screw plug on the cooling air connection and fit the cooling air line.
General
u Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
ter residues and clean it. Remove any foreign objects that may be present.
u Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
u Put engine-side oil circulation to the turbocharger into operation.
u Prepare the turbocharger for operation (see Checks before commissioning 22).
u The turbocharger is now ready for operation.