4 Commissioning / 4.3 Commissioning after taking out of operation
© Copyright 2021 ABB. All rights reserved. HZTL4037_EN Rev.F May 2021
4.3 Commissioning after taking out of operation
If present
u Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
gas outlet.
u Remove the locking screws on the water connections and fit the water pipe.
General
u Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
ter residues and clean it. Remove any foreign objects that may be present.
u Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
u Put engine-side oil circulation to the turbocharger into operation.
u Prepare the turbocharger for operation (see Checks before commissioning →35).
u The turbocharger is now ready for operation.