IEC07000188 V1 EN
Figure 55: Test of RTC with I/O
12.16 Basic IED functions
12.16.1 Parameter setting group handling SETGRPS
Prepare the IED for verification of settings as outlined in section "Preparing for test"
in this chapter.
12.16.1.1 Verifying the settings
1. Check the configuration of binary inputs that control the selection of the active
setting group.
2. Browse to the ActiveGroup menu to achieve information about the active
setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test/
Function status/Setting groups/ActiveGroup
3. Connect the appropriate dc voltage to the corresponding binary input of the IED
and observe the information presented on the local HMI.
The displayed information must always correspond to the activated input.
4. Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting
groups are described in the corresponding PCM600 documents and instructions
for the operators within the SCS are included in the SCS documentation.
1MRK502053-UEN B Section 12
Testing functionality by secondary injection
Generator protection REG670 2.0 IEC 235
Commissioning manual