1. To view the reports, go to the Auditing tab.
IEC11000049-1-en.vsd
GUID-8348F60B-9BF5-4018-9740-0FA3371B0F9F V1 EN
Figure 26: Auditing tab
2. Open and view each report.
3. View reports in one of the following ways:
In the short cut menu, right click and select View report.
Click the View report button in the upper right corner of the auditing
screen.
Double click a report record.
4. Delete reports in one of the following ways:
In the short cut menu, right click and select Delete report.
Click the Delete report button in the upper right corner of the auditing
screen.
Select a record with the mouse cursor then press the Delete key on the
keyboard.
5. Generate logs in one of the following ways:
In the short cut menu, right click and select Generate log.
Click the Generate log button.
Besides generating a report you can also generate a log file with the same
information as for the report. Open and see the details of the file in Notepad or
MS Excel.
After a successful generation of the log, the system confirms with a message
along with the path of the log file.
1MRK502053-UEN B Section 7
Calibrating injection based 100% stator earth fault protection
Generator protection REG670 2.0 IEC 81
Commissioning manual