The settings for each function must be calculated before the commissioning task can start. A
configuration, done in the configuration and programming tool, must also be available if the IED
does not have a factory configuration downloaded.
The IED is unpacked and visually checked. It is preferably mounted in a cubicle or on a wall.
The connection to the protection system has to be checked in order to verify that the installation
is successful.