Mounting methods and details Chapter 5
Installing the IED
3.6 Side-by-side flush mounting
It is not recommended to flush mount side by side mounted cases. If your application demands
this type of installation, use the side-by-side mounting details kit and the 19” panel mounting
kit. The maximum size of the panel cut out is 19”.
3.6.1 Side-by-side flush mounting details
Figure 14: Side-by-side flush mounting details.
Mounting procedure for side-by-side flush mounting
Procedure
1. Place the two IEDs next to each other on a flat surface
Note!
With side-by-side flush mounting installation, only IP class 20 is obtained. To reach the IP class
54 the case-by-case flush mounting is recommended. See section, flush mounting.
PosNo Description
1 Two mounting plates
2 Eight screws
3 Eight fixing screws
4 Two mounting angles
xx04000457.vsd
19"
1
2
3