5 - 2 WBPEEUI240751C0
Unpacking and Inspection
7. Do Not Use Lead Pencils to Set Switches
Do Not Use Lead Pencils to Set SwitchesDo Not Use Lead Pencils to Set Switches
Do Not Use Lead Pencils to Set Switches. To avoid con-
tamination of switch contacts that can result in unnecessary
circuit board malfunction, do not use a lead pencil to set a
switch.
Unpacking and Inspection
1. Examine the hardware immediately to verify that it has not
been damaged in transit.
2. Notify the nearest ABB sales office of any damage.
3. File a claim for any damage with the transportation com-
pany that handled the shipment.
4. Use the original packing material and container to store
the hardware.
5. Store the hardware in an environment of good air quality,
free from temperature and moisture extremes and corrosives.
Installation Procedures
Table 5-1 lists all of the I/O and auxiliary block installation
procedures. Refer to Installation and Connection Sequence
Installation and Connection SequenceInstallation and Connection Sequence
Installation and Connection Sequence in
this section for an explanation of how to use the procedure
sections.
Table 5-1. Installation Procedures
Procedure Description
PR1 I nstallation preparation
PR2 I/O block base installation
PR3 I/O module installation
PR4 Auxiliary block installation
PR5 BLK-100 installation
PR6 AI N-120 setup
PR7 AI N-200 setup
PR8 AI N-220 setup
PR9 AI N-300 setup
PR10 AOT-150 setup
PR11 CIO-100 setup