4.2.4 Service work every 8000 … 16000 hours
The inspection and assessment of the rotor and the bearing parts must
be carried out by an official ABB Turbocharging service station.
u Disassemble turbocharger.
u Measure clearances.
u Clean the turbine and compressor wheels and inspect for damage.
u Clean the turbine and compressor casings and inspect for any cracks
and erosion or corrosion.
u Clean bearing casing and blow air through oil ports.
u Clean nozzle ring and check for cracks and erosion.
u Inspect and assess bearing parts and rotor.
4.2.5 Service work every 24000 … 36000 hours
The replacement of bearing parts and the inspection and assessment of
the rotor must be carried out by an ABB Turbocharging Service Station.
u Disassemble turbocharger.
u Clearance measurement.
u Clean the turbine and compressor wheels and inspect for damage.
u Clean turbine casing as well as compressor casing and check for any
cracks and erosion or corrosion.
u Clean bearing casing and blow air through oil ports.
u Clean nozzle ring and check for cracks and erosion.
u Dismantle, inspect and balance the rotor.
u Replace plain bearings with original parts from ABB Turbocharging.