Operation Manual / TPL65VA32/33
Commissioning
3
Commissio
ning after taking out of
operation
3.3
Page 40
© Copyright 2015 ABB. All rights rese
rved.
September 2015 HZTL2464_EN Revision C
Commissioning after taking out of operation
3.3
Remove cover plates (blind flanges) between compressor casing
outlet and charge air duct, before gas inlet and after gas outlet.
Inspect exhaust gas duct / line in front of and after turbine for any
combustion deposits, foreign matter or residual water. Clean and
remove.
Inspect air supply line or filter silencer for any foreign matter. Clean
and remove.
Start up turbocharger oil circulation system at engine end.
Prepare turbocharger for operation as instructed in section "Inspection
work before start-up / commissioning" of chapter headed "Start-up /
commissioning".
Start up turbocharger.
TPL65: Version with compressor wheel cooling system
Remove screw plug on cooling air connection and fit cooling air line.
3.3
If provided