Subject to Export Control, see Cover Page for details. 2-17
2-3-4. VERIFICATION PROCEDURES
A. Generator Verification
TEST EQUIPMENT: Power Meter w/ Sensor
NOTE
Results of the Generator Verification Procedure can be recorded on the
Verification Data Sheets.
1. Press POWER Key to turn ON the Test Set. Allow Test Set to warm up before continuing
with Verification Procedure.
2. With the System Menu displayed, press the 2 Key to display the Receiver Test Screen.
T/R CONNECTOR
3. Move the cursor to the MHz: field.
4. Press the F1 “Edit” Key to highlight the field. Press the 2 Key to set the field to 2 MHz.
Press the F1 “Done” Key to store the setting.
5. Move the cursor to the Port: field.
6. Press the F1 “Edit” Key to highlight the field. Using the Arrow Keys ( ), select T/R.
Press the F1 “Done” Key to store the setting.
7. Move the cursor to the Level: field.
8. Press the F1 “Edit” Key to highlight the field. Press the ± Key, 5 Key and 0 Key to set the
field to -50.0 dBm. Press the F1 “Done” Key to store the setting.
9. Insure Power Meter Sensor range covers -50 dBm. Zero and calibrate the Power Meter.
10. Connect the Power Meter Sensor to the T/R Connector with TNC/N Adapter.
11. Record Power Meter reading.
12. Move the cursor to the MHz: field.
13. Press the F1 “Edit” Key to highlight the field. Press the 2 Key and 0 Key to set the field to
20 MHz. Press the F1 “Done” Key to store the setting.
14. Record Power Meter reading.
15. Repeat Steps 12 to 14 for the following frequencies:
100 MHz
200 MHz
300 MHz
400 MHz
500 MHz
600 MHz
700 MHz
800 MHz
900 MHz
1000 MHz
ANT CONNECTOR
16. Move the cursor to the Port: field.
17. Press the F1 “Edit” Key to highlight the field. Using the Arrow Keys ( ), select ANT.
Press the F1 “Done” Key to store the setting.