3. Connecting to the Gas Network
3.5.3 Designated Boundary Connection Areas
Some areas in the Perth hills are designated as boundary connection areas. In these areas, the
standard gas meter box should be located on the main fronting boundary line of the property
and an open trench provided to the gas meter box position.
Your gas retailer will advise you if your site is a Designated Boundary Connection Area.
3.5.4 Gas Services to Large Rural or Semi-Rural Lots
The gas meter box should be mounted on the main fronting boundary line of the property.
Alternatively, it may be mounted on the primary building in a suitable, compliant position.
Additional charges may apply for services over 20m in length.
All the following conditions must be met:
A suitable straight and direct trench is to be provided from the boundary to the gas meter
location by the Responsible Person.
The route shall, as far as practicable, be at right angles to the gas main or as directed by
AGA.
The bed of the trench shall be soil that is free from rock or other sharp formation that may
cause damage to the Polyethylene (PE) gas service pipe.
The minimum depth of cover is 600mm.
A front boundary connection is the preferred option when the Building Frontage is
greater than 20m from the boundary line.
3.5.5 Connection to ,Commercial Properties (AL8, AL12 or AL18
Gas Meters)
For a new gas connection to a commercial property requiring an AL8 or AL12 gas meter, refer
to the Connection Process Handbook.
Installation of an AL18 gas meter, or greater, requires a Commercial Gas Request (CGR) to be
submitted to AGA. Refer to the link below for further information:
http://www.atcogas.com.au/For-Business/Connecting-to-Our-Network/
The siting of AL8, AL12 and AL18 gas meters for commercial properties is subject to the
conditions detailed in this document. Where possible, gas meter boxes for commercial
properties should be mounted on the boundary in a protected location.
Approval for commercial gas meter locations will be subject to site inspection and assessment
by AGA Construction Department. Contact AGA Scheduling with any enquiries.
Where gas meter box is not located on the boundary, an open trench may be required.
11

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the atco gas AL8 and is the answer not in the manual?

atco gas AL8 Specifications

General IconGeneral
Brandatco gas
ModelAL8
CategoryMeasuring Instruments
LanguageEnglish