Use and maintenance manual pag. 15
2 Machine setting up
2.1 Preliminary operations
Before connecting up the machine, ensure that the factory voltage corresponds to the one indicated on the
label fixed on the left side of the machine (Fig. 1).
If, for any reason, the voltage of the motors should be changed (pump and trolley translation), it is
imperative to adapt the transformer voltage to the desired one, moving the pertinent wire.
Carry out this operation with the machine completely disconnected from the electric network !
2.2 Machine setting up
The machine is delivered already tested in our factory, with the right quantity of oil (50 Kg approx.) and the
electric motors (pump and trolley translation) connected to the requested voltage.
On first switching on of the machine, through the main switch (A), the pump rotation direction is correct if:
Fig. 1
Fig. 2
(A)