11.6 Commissioning log
The Logano G515 can be used with an oil or gas-fired burner. Fill in the
commissioning log for the appropriate type of oil or gas burner carefully.
▶ Sign all start-up work as completed and enter the relevant date.
Commissioning operations Individual steps Comments (signature)
1. Perform leak test of the entire system
2. Fill the heating system with water page 35
3. Purge the air from the heating system
4. Perform the leak test if the boiler was assembled on-site page 19
5. Record the filling water quantity and composition in the operator’s log
(included with the technical documentation).
6. Check position of heat exchanger baffles page 22
7. Check the fuel line for leaks.
8. Start up the control panel page 35
9. Initial burner start-up See burner
documentation
10. Check the flue gas temperature page 36
11. Check vent pipe for leaks.
12. Check the boiler and flue gas side for leaks
13. Enter the fuel used in the table provided in the operating instructions.
14. Inform the owner and operator and hand over technical documentation
15. Confirm properly-completed commissioning
Company stamp/signature/date