p. 10 - Manual FA01719-EN - 03/2022 - © CAME S.p.A. - Translated original instructions
Remove the nut and washer from the bolts
Fit the electric cables into the tubes so that they come out about 600 mm.
Fill the foundation frame with concrete. The plate must be perfectly level with the bolts which are entirely above
surface.
Wait at least 24 hrs for the concrete to solidify.
Remove the foundation frame and fill the hole with earth around the concrete block.
If the rack is already there, place the anchoring plate, being careful to respect the measurements shown in the
drawing.
Careful! The tubes must pass through their corresponding holes.