Fig. 34 — Installed Barometric Hood Side View and Isometric View
BAROMETRIC HOOD (HORIZONTAL CONFIGURATION) 
For  horizontal  return  and  field-installed  economizer,  install  the
economizer as follows:
1. Install the field provided horizontal ductwork onto the unit.
Duct height must be at least 19-1/2 in. high, however the duct
can  be  no  taller  than  the  top  of  the  relief  opening  in  the
bottom  panel,  or  airflow  into  the  outside  air  hood  will  be
restricted. (See Fig. 35.)
2. Cut a 16 in. x 36 in. opening in the return duct for the relief
damper. (See Fig. 35).
3. On the field installed economizer (CRECOMZR0**A00), a
birdscreen  or  hardware  cloth  is  shipped  attached  to  the
bottom panel used for vertical applications. 
NOTE: This panel is not used for horizontal return applications.
Remove the screen from the provided panel and install it over the
relief opening cut in return duct.
4. Using the  blade brackets,  install  the relief damper onto the
side of  the  return duct (see Fig.  36). The two brackets and
relief damper are provided with the economizer. 
5. Using  the  provided  hardware,  screw  the
CRBARHOD001A00  hood  sides  and  top  together.  (See
Fig. 37.)
Fig. 35 — Relief Damper
Unit
Outside
Air Hood
Min
19 1/2"
Relief 
Opening
Return 
Duct
16"
1"
18 3/8"