8. Critical Installation Checklist
SECTION 8 CRITICAL INSTALLATION CHECKLIST
The following is a list of critical requirements that must be adhered to in order to ensure
reliable operation of your VANTAGE operator(s):
Ensure that the Wall Bracket is securely anchored
Make sure that the operators maximum stroke is being utilised
Only use V-Series cable for the installation
Leave a 350mm long loop in the cable
Fit an electric gate lock if the leaf width is greater than 3 metres
Ensure that the opening and closing angles conform to the installation guidelines
Ensure that your gate and operator(s) are equipped to deal with Wind Loading
(refer to the Table 6 and 7 on page 14)
Never run the operator directly from the battery! Doing so will cause
damage to the operator. Only run the operator from the V-Series
Controller.