MAN. 126 rev.4 Use and maintenance manual S19
27 of 77
4.3.2
Loading/unloading with a crane
To load/unload the platform, it is also possible to use a mobile crane of
adequate capacity. To proceed with this operation use a 4 way sling of
sufficient size, capacity and equal length to raise the MEWP by the
illustrated connections on the outriggers.
Picture 21: MEWP crane lift points
Lifting operations are only to be carried out with the MEWP
outriggers in the closed position.
Be careful not to damage railings and or parts of machine.
Always use personal protection equipment, including hand
protection. Do not handle ropes or chains without gloves.
All personnel should maintain a safe distance. No personnel
should ever stand below a suspended weight.
Always insure that you comply with DOT safety rules relevant to
width, height, weight.
Always carefully check and pay attention to vehicle height signs
along travel route, especially when travelling in tight quarters
including galleries, bridges, electrical and phone lines .