A24 Coffee boiler 1 time out alarm
- Time allocated to the coffee
boiler 1 heating exceeded.
- Check the t° probe
- Check the probe connection
- Check the electronic board
- Check the heater and the relay
- Check the programmed heating time
- Check the relay control box
A25 Coffee boiler 2 time out alarm
- Time allocated to the coffee
boiler 2 heating exceeded.
- Check the t° probe
- Check the probe connection
- Check the electronic board
- Check the heater and the relay
- Check the programmed heating time
- Check the relay control box
A26 Coffee boiler 3 time out alarm
- Time allocated to the coffee
boiler 3 heating exceeded.
- Check the t° probe
- Check the probe connection
- Check the electronic board
- Check the heater and the relay
- Check the programmed heating time
- Check the relay control box
A27 Flow meter 1 time out alarm
- No flowmeter 1 pulse after 5
seconds
- Check the flowmeter (flashings)
- Check the flowmeter connection
- Check the electronic board
- Check for clogged coffee group
A28 Flow meter 2 time out alarm
- No flowmeter 2 pulse after 5
seconds
- Check the flowmeter (flashings)
- Check the flowmeter connection
- Check the electronic board
- Check for clogged coffee group
A29 Flow meter 3 time out alarm
- No flowmeter 3 pulse after 5
seconds
- Check the flowmeter (flashings)
- Check the flowmeter connection
- Check the electronic board
- Check for clogged coffee group