Fig.17
25: Place both 8-rung frames;
26: Place locking pins between the
frames themselves;
27: Place two Safe Guard guardrail frames
on the upper rung: one
to façade side, the other in
the middle of the rungs. Click the
diagonal ledgers in place on the 5
th
rung of the frame in question;
Fig.18
28: Place the platform with hatch (on the
5
th
rung from the top) to façade side;
slide both blow-away protections
under the rung;
29: Repeat steps 24 - 28 until
the preferred level has been reached;
Fig.19
Caution! When the preferred level has
been reached it must be completely
closed:
30: Place the platform without hatch
to the “street side”; slide both
blow-away protections under the
rung; and then place the platform with
hatch to the façade side.