Test Run ESIE11-05
208 Commissioning and Test Run
1. Test Run
1.1 Installation Process
Below figure shows the installation process. Install in the order of the steps shown.
Selection of Location
Inspecting and Handling the Unit
Placing the Unit
Field Wiring
Pipe Insulation
Checking of Device and Installation Conditions
Test Run
Operations which require the
power to be turned on.