Test Run ESIE11-05
212 Commissioning and Test Run
1.3 Operation when Power is Turned On
1.3.1 When Turning On Power First Time
The unit cannot be run for up to 12 minutes to automatically set the master power and address.
Status
1.3.2 Hydrobox or Outdoor Unit PCB Has Been Changed
Be sure to push and hold the RESET button for 5 seconds. If not, the addition cannot be
recognized. In this case, the unit cannot be run for up to 12 minutes to automatically set the
address.
Status
Caution When the 400 volt power supply is applied to ā€œNā€ phase by mistake, replace Inverter PCB (A2P)
and control transformer (T1R, T2R) in switch box together.
Outdoor unit Test lamp H2P .... Blinks
Can also be set during operation described above.
Hydrobox If ON button is pushed during operation described above, the "UH"
malfunction indicator blinks.
(Returns to normal when automatic setting is complete.)
Outdoor unit Test lamp H2P .... ON
Can also be set during operation described above.
Hydrobox If ON button is pushed during operation described above, the "UH" or "U4"
malfunction indicator blinks. (Returns to normal when automatic setting is
complete.)
Switch box cover
Service cover
[Service Precautions] label
Switch box
(the upper right)