SiUS091601EA Pump Down Operation
Part 7 Trial Operation and Field Settings 198
Reference
1. Pump Down Operation
Outline In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing of the unit.
Details 1. Remove the valve caps from the liquid stop valve and the gas stop valve.
2. Carry out forced cooling operation.
3. After 5 to10 minutes, close the liquid stop valve with a hexagonal wrench.
4. After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to Forced Cooling Operation on page 199 for details.
Gas stop valve
Valve cap
Close
Liquid stop valve
Service port
(R25008)
Hexagonal
wrench

Table of Contents

Other manuals for Daikin FDMQ-R Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin FDMQ-R Series and is the answer not in the manual?

Daikin FDMQ-R Series Specifications

General IconGeneral
BrandDaikin
ModelFDMQ-R Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals