E – Mechanical Installation
April, 2018 E-8 INM.XX.X.00
Mechanical Installation – Special Cases
Some equipment may have additional/optional arrangements – refer to submittal documentation and equipment
accompanying factory instructions.
Frame-mounted main blower shipping brackets.
For shipping purposes, larger (7 HP and up) direct-driven main blower frame springs are affixed with shipping
brackets (see Pic. E.8). This normally applies to LD series dehumidifiers only.
Upon installation remove ONLY lower bolt from all four corners (detail A) at the frame base - removing these
bolts ensures that the blower vibration is dampened correctly.
If the blower frame includes two blowers (stack), in addition to
base bolts removal (described above) remove ONE bolt from
each bracket at the wall springs (B).
Pic. E.8