2. Push the blue slide release lock tabs forward on both rails and slide the system
into the cabinet. The slam latches will engage to secure the system in the
cabinet.
Figure 40 Slide the system into the cabinet
Connect the I/O cables and power cords
This procedure is used to connect the peripherals and power to the system.
Procedure
1. Using the connection information recorded on the labels, connect the I/O
cables to the system.
2. Plug the power cords into the power supplies.
Verifying successful M.2 card replacement from the ACM
After an M.2 card is replaced and power has been re-applied, you can run the FRU
command line verification from the ACM to ensure that the replacement was
successful.
Procedure
1. From the ACM, type the following command: # showfru boss
The screen displays that the system is collecting data. When the data collection
is completed, the screen displays status information for the BOSS card and
both M.2 cards.
acme-dp4400-ACM:~ # showfru boss
Collecting Data............
_____________________________________
| ID | State| Status| FW Version |
|====================================|
| BOSS-S1| 0 | OK | 2.5.13.2008|
________________________________________________________________
| ID | State | Status| FW Version| Capacity| Operation| OpStatus|
Remove and replace assemblies
50 Dell EMC Integrated Data Protection Appliance DP4400 2.4 Service Procedures Guide