Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01 43
1. If not already accomplished, use a forklift or pallet jack to move the I/O and ISBM/PM sections to the
installation area, or as close as possible, before unloading from the pallets.
If possible, move each section using the pallet. Insert the forklift or pallet jack forks from the right side of
the pallet (facing the cabinet), between the supports on the bottom of the pallet (see for the I/O and ISBM/
PM section center of gravity measurements). If the sections must be moved using the cabinet front or rear
fork lift slots, see the caution statements at the beginning of this procedure. See Figure 20 for cabinet fork
lift slots locations.
2. Remove the three bolts securing the left side shipping bracket to the ISBM/PM cabinet and three bolts
securing the bracket to the pallet (see Figure 16). Remove the left side shipping bracket.
3. Remove the three bolts securing the right side shipping bracket to the ISBM/PM cabinet and three bolts
securing the bracket to the pallet (see Figure 17). Remove the right side shipping bracket.
Figure 16. Removing the ISBM/PM Section Left Side Shipping Bracket
Front Door
Left Side Shipping
Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Dress Skirt
(Three sides, Optional)
UPS System Installation

Table of Contents

Related product manuals