Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01 55
Figure 26. I/O and ISBM/PM in Position
ISBM/PM SECTIONI/O SECTION
Ground Points
44..44 BBaatttteerryy SSyysstteemm IInnssttaallllaattiioonn
If installing a battery system, install the customer-supplied battery system according to the battery and battery
system manufacturer's instructions and all applicable codes and regulations, including the NEC, Article 480.
After the battery system is installed, proceed to paragraph
4.6 Installing UPS External and Battery Power Wiring.
44..55 DDiissttrriibbuutteedd BByyppaassss TTiiee CCaabbiinneett IInnssttaallllaattiioonn
NOTE The tie cabinet must contain Module Output Breakers (MOBs) with dual auxiliary
contacts for control of the system.
If installing a distributed bypass system, install the customer-supplied tie cabinet or distribution panel according
to the tie cabinet or distribution panel manufacturer's instructions and all applicable codes and regulations,
including the NEC, Article 480. After the tie cabinet is installed, proceed to paragraph
4.8 Installing a REPO Switch to complete the wiring of the UPS.
44..66 IInnssttaalllliinngg UUPPSS EExxtteerrnnaall aanndd BBaatttteerryy PPoowweerr WWiirriinngg
NOTE The ISBM/PM section is shipped with debris shields covering the ventilation grills on top
of the sections (see Figure 27). Do not remove the debris shields until installation is
complete. However, remove the shields before operating the UPS. Once the debris
shields are removed, do not place objects on the ventilation grills.
UPS System Installation