Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01 69
1. If not already installed, install the LAN drops.
2. Unfasten the front door latch and swing the door open (see Figure 16).
3. Remove a UPS top cabinet interface entry conduit landing plate(s) as required to drill or punch holes (see
Figure 28).
4. Reinstall the interface entry plates and install the conduit.
5. Route and connect the LAN, telephone, and other cables to the appropriate Minislot cards. See Figure 32
and Figure 37 for Minislot communication bay locations.
6. Close the front door and secure the latch.
7. Refer to the manual supplied with the Minislot card for operator instructions.
Figure 37. Minislot Communication Bays
Minislot Commnunication Bay 1
Minislot Commnunication Bay 2
Minislot Commnunication Bay 3
Minislot Commnunication Bay 4
TB1
TB2
TB3
44..88 IInnssttaalllliinngg aa RREEPPOO SSwwiittcchh
A latching-type Remote Emergency Power-off (REPO) switch can be used in an emergency to shut down the
UPS and remove power to the critical load from a location away from where the UPS is installed. Figure 38
shows a REPO switch.
NOTE Before installing a REPO switch, verify that the UPS was installed according to the
instructions in paragraphs 4.2 Unloading the UPS Cabinet from the Pallet through
4.7 Installing Interface Connections.
NOTE When installing the REPO switch, you must install conduit between the device and the
UPS cabinet for wiring the switch.
UPS System Installation