Loading...
5. All piping connections are tight.
6. Piping routed to prevent chafing and rub-through.
7. Piping has been evacuated and refrigerant charge added (if required).
8. Line voltage to power wiring matches equipment nameplate.
9. Power wiring connections completed, including earth ground.
10. Power line circuit breakers or fuses have proper ratings for equipment installed.
11. Control wiring connections completed.
12. All wiring connections are tight.
13. Foreign materials have been removed from area: in and around all equipment installed
(shipping materials, construction materials, tools, etc.).
14. Fans and blowers rotate freely and in the proper direction.
15. Blank startup sheet has been sent with the evaporator unit and is ready to be completed by
the installer.
Vertiv | Liebert PFH Installer/User Guide | 27